on 04-21-2009 3:24 PM
Hi all,
In standard way can cost analysis be done in order & task list ---
1. at operation level
2.cost at object level distribution
3.cost distribution to object list is possible.
pl expalin in details .thanks in advance
rgds
rajib
hi
you can do the cost analysis for order and task list level only .if you want to cost at operation level i think you have to use the add on .kindly browse the forum you can find the same
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Basically Compatible units are ment for operation level costing.
If you need futher information revert back.
Rgds
Sudhir Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can try MCI8 in the PMIS reporting for costs by order type, equipment or functional location. To get costing for task lists used in maintenance plans try IP24 or IP31.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For operation level costing, I am not sure but I read it in this forum only taht it is possible thru' 'Compatible Unit Management'. Pls explore this.
For object list , about cost distribution not sure.....but yeah settlement for various account assignement in object list is possible thru' customer exit IW.....27(pls check detail in SAP enhancement list.
Regards,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.