Dear friends,

i have one problem , i am not able to see the break up of WIP valuation.Under the WIP how much OVH, mat and labour cost booked un the production order.

my company's scenario is product cost by order and when i put the t-code kkax, only able to see total figure of WIP not breakup wise and getting message " WIP explanation only available for valuation at target cost".

But product by order is only at actual cost.

pls let me what is the solution to get the WIP report break up wise.

for exp. WIP = rs10000

which mat = rs2000

OVH = rs5000

Lab =Rs3000

Total =rs10000

awaiting for your reply