Budget check at SC level in SRM 4

Experts,

How can i implemet the below functionlity :

"Budget checking for multiples Cost Center and internal order Numbers". Do i need to use the 'BBP_BUDGET_CHECK'.

Plz let me know.

Rgrds,

SK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 21, 2009 at 01:03 PM

    Hi,

    The SRM budget check is a standard functionnality for internal order and project.

    You don't need to use a badi to make it work.

    Just configure ECC and SRM.

    There is no standard functionality to get budget check on cost center...

    Kind regards,

    Yann

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Yann,

      Appreciate your response.

      Is it also same for Asset A/c assignment as well? The system by default takes care of the budget check , once SRM/EC is inegrated ?....

      Any idea, in which table budget related data is stored in SAP SRM?

      Once again thanks!

      Rgrds,

      SK