Logic in determining package sequence in maintenance planning

541 Views

Hi,

I have created a performance based strategy, with the package containing 2 cycles and 2 levels of hierarchy.

cycle 1 500H

cycle 2 1000H

So, the package sequence is showing

500H 1000H 1500H 2000H 2500H etc

1 2 1 2 1 etc

When I tested with measuring documents, I noticed that the package due always following the sequence of the cycle 1,2,1,2,1,2, regardless of the the measurement reading. The example I tested with the measuring document is as follows:-

SAP assigned package due in IP10

1st measdoc = 600H 1

2nd measdoc = 1500H 2

3rd measdoc = 2500H 1

4th measdoc = 2520H 2

I thought, based on the packages defined in the strategy, I should be getting the package due as 1,1, 2,1, which is based on the difference between last reading and current reading.

Can someone shed some light on how SAP determine the Package due ?

Thanks !