Former Member
Apr 20, 2009 at 02:36 PM

MRP Question

169 Views

Hello,

I want to create a purchase requistion already fixed/firmed. To do this, I have created a material with MRP type P1: MRP, fixing type -1- but the purchase requisition is not created fixed/firmed because is created after the End of planning time fence. I have one possibility: when I run MD03 with the option display result before saving, in the planning result, set up the firming date before the end of planning time fence. In this way I can create the purchase requisition already fixed but I have to made it manually.

The question is: where I can set up the system in order to manage automatically the firming date in order to have the purchase requisition always fixed/firmed ?

Thanks.

Bye

MRP1 Screen of master data

Base unit of measure PC

Purchasing group 401

Plant-sp.matl status

MRP type P1 MRP, fixing type -1-

Reorder point Planning time fence 30

Planning cycle MRP controller