on 04-20-2009 12:35 PM
dear all,
I need to transfer my current PR,PO commitment budget to next fisical year.
I have to carryfarward only PO,PR commitment budget to next year.
is there any way to do this.
Sukhveer.
Dear,
I think in standard sap you can not carryforward only PR,PO commitment budget amount.
Here system will carryforward whatever available budget of project, from current fiscal year to next fiscal year.This you can not do at WBS Element level. It is possible only for Project level.
& same thing with commitment, whatever open commitment is avail will carryforward to next fiscal year.
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try CJ34 transaction for Transfer of budget. By this you can transfer WBS Element wise.
Sandeep.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sukhveer,
You can carryforwrd PR & PO commitments and Balance Budget to next Fiscal year by using following transactions.
1) Logistics > Project System > Financials > Year-End Closing > CJCF - Carry Forward Commitment
2) Logistics > Project System > Financials > Year-End Closing > CJCO - Budget Carryforward
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use Transaction CJCO for Carryforward Budget
and CJCF for Carry Forwarding Commitments.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.