dear all,

I need to transfer my current PR,PO commitment budget to next fisical year.

I have to carryfarward only PO,PR commitment budget to next year.

is there any way to do this.

Sukhveer.

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Dear,

I think in standard sap you can not carryforward only PR,PO commitment budget amount.

Here system will carryforward whatever available budget of project, from current fiscal year to next fiscal year.This you can not do at WBS Element level. It is possible only for Project level.

& same thing with commitment, whatever open commitment is avail will carryforward to next fiscal year.

Sandeep

Former Member
0 Kudos

thanks for ur advices,

But if there is any solution plz give ur comments.

Sukhveer.

Answers (4)

Answers (4)

Former Member
0 Kudos

Closed

stheurkar
Active Contributor
0 Kudos

Hi,

Try CJ34 transaction for Transfer of budget. By this you can transfer WBS Element wise.

Sandeep.

Former Member
0 Kudos

Dear,

I need to carryfarward only PR,PO commitment budget amount.Not all budget how can i transfer only pr,po commitment .

Sukhveer.

stheurkar
Active Contributor
0 Kudos

Dear Sukhveer,

You can carryforwrd PR & PO commitments and Balance Budget to next Fiscal year by using following transactions.

1) Logistics > Project System > Financials > Year-End Closing > CJCF - Carry Forward Commitment

2) Logistics > Project System > Financials > Year-End Closing > CJCO - Budget Carryforward

Regards,

Sandeep

Former Member
0 Kudos

Hi,

Use Transaction CJCO for Carryforward Budget

and CJCF for Carry Forwarding Commitments.

Regards,

Nitin

Former Member
0 Kudos

Dear,

I know that t code but i need to transfer for few wbs elements not for whole project.

These t codes for carryfarward for whole project.

Need ur feedback.