Hello all,
In MD06 a material is not showing up the red light. All traffic lights are correctly defined.
Actually this material has Planned Delivery Time being defined in Material master as 45 days and there is only next 4-5 days stock left, still the material is showing up green in MD06. And there is requirement for the whole month being displayed in MD06.
What may be the possible reasons??
Regards,
Robin.