Dear GURU's ,
How to close a project , if all the WBS are settled ? what is technically completed?
Regards,
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hiu2026
Prerequisites
You can only set the Closed status after Released status.
If u want to close the project/wbsu2026plz follow
Technically completed (TECO)
We can use this status for WBS elements that are completed from a technical point of view, but where you still expect costs to accrue.
Cj20nu2026Editu2026..Statusu2026.Complete technicallyu2026..set./undo(revoke)
Closed (CLSD)
We can use this status for a work breakdown structure or WBS element that has been completed from both a logistic and an accounting point of view.
Cj20nu2026.Editu2026..Statusu2026.Closeu2026..set./undo(revoke)
Both status can revoke.
Refer this link
http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm
Refer Status mng
Regards
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.