Hi,

I have the following scenario regarding consumption of project stock,

1. Material is purchased into project stock with reference to a WBS element.

2. Good receipt is posted correctly that Actual Cost is reflected on the stock-WBS element.

3. Now, I'd like to consume the project stock by the network activity. So I did a MB1A of movement type 281 Q to the consuming network-activity. However, there is no accounting document generated at the step. The cost is not actualized on the network-activity.

The project is with valuated stock.

Am I doing the right step in terms of consumption of project stock?

How can I actualize the cost to the network-activity by consumption of project stock?

Any suggestion would be greatly appreciated.

Thanks,

Ting

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ting,

Please check GBB in tcode OBYC and check whether the GL assigned to account modifier VBR and then check the assignment of VBR with the Movement type 281 Q.

Regards,

Muzamil

former_member203108
Active Contributor
0 Kudos

Check if the network is activity account assigned..and also run actual cost report CJI3 and have look where the cost has been debited...