matearial ATP checks

Former Member
0 Kudos

HI experts,

I have a scenario as mentioned below--

there are two plants say one is 500 & another is 600.planning plant is 600.now in plant 500 there are 5 p/cs & in plant 600 another 5 p/cs available material & i need to create maintenance order for plant 500 , for which I need 10 p/cs of material.so whether system will check material availability for both plants & will create reservation for 10 p/cs? or it will check only for plant 500 & will create reservation only for 5 p/cs?please explain in details.thanks in advance.

rgds

rajib

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This means your material is defined at both plant levels 500 and 600.Does both plant level materials have availability check in MRP data.As in MM availability check happens at plant level-storage location level for reservations even if in PM we define availabilty check scope at order type which is at planning plant level actual check depneds on material master parameters.

Hence it should happen on plant level and not on planning plant level.But I am not sure n this,get help from MM guys.Reason is they define requirements parameters for reservations and that is governing parameter

regards,

atul

Former Member
0 Kudos

hi experts

can anyone please give some details on this which one is correct?

rgds

rajib

former_member187991
Active Contributor
0 Kudos

hi

Materials are created based on plant level only ,also in IMG you are defining the scope of check which is assinged to the material master record defined at plant level only .

regards

thyagarajan

Former Member
0 Kudos

thanks expert for your valuable input.

rgds

mehbub

Answers (2)

Answers (2)

MTerence
Active Contributor
0 Kudos

Hi

Check whether planning plant 600 is assigned for both 500 and 600 plant. If that so.. you can use the materials from another plant also...

Avability check will takes place with respect to plant and order type... i think... u can proceed with this.

- Pithan

Former Member
0 Kudos

hi,

if your planning plant 600 is assigned to MP 500 and then you would creating MO in planning plant for technical object existing in MP 500 .. and Material avialaibility chek would happen for materials in planning plant becoz in spro for a combination of order type and avialabilty type you would assign the scope of check and order type is assigned to planning plant .. chek this ..

regrds

pushpa