How to Close a Goods Receipt PO '"Open for landed cost "

Nov 10, 2016 at 10:42 AM

43

avatar image

Hi All ,

I have updated one Goods Receipt PO Open for Landed cost by mistake . How can I close this . Now it showing in the list of Goods Receipt PO in Landed Cost .

Regards

Reena

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Pradnya S Nov 10, 2016 at 02:21 PM
0

Hi Reena,

In SAP when you create a document, it remains open till it is copied on to the next level. So GRPO will remain open till you copy it to either A/P Invoice, Landed Cost if you want to take it ahead.

In case there is some error in quantity or rate or anything then you can file a goods return document.

Only then the GRPO will get closed.

Regards

Pradnya