Hi All,

IN MFBF while doing the Assembly backflushing, I am getting the Child component qty separate line item if i consume less than BOM requirement. For example for making A header material 100kg, Child Component Material B is required 110 kg as per bom, but in process the actual consumption was 105kg , while correcting the proposed qty to 105, the system is giving 5kg in separate line item which is not required by client, how to control the same. What setting has to be done for the same. Pls let me know.

thanks in advance.

regards

arjunan