Dear All,

I want to change my planning strategy for FERT material from 20 to 10 (i.e MTS from present MTO).

Current field in MM.

MRP Type - PD

Strategy group - 10

My requirement are as under,

I want that after posting Sales order in SD and taking MRP run, all the unrestricted stock should first get allocated to the order and then system should raise Planned order for shortages.

Want to set reorder level with Min & Max quantities for production so as when the reorder level hits the system generates the planned order for Max quantities for production.

Kindly give your feedback how to do the same.