on 04-14-2009 12:15 PM
Dear SAPians,
I want to maintain the SLED/BBD Date for the few incoming materials and during Usage Decision we want to enter it. But at present its option to enter the SLED Date in UD recording window is not coming. Please giude that how can i do it?
Thanks in Advance.
Regards.
A.Mittal
Dear Attul
First maintain Shelf life data in Material master in Plant data/ Storage 1 view. Once you enter the min shelf life and maximum shelf life you will get the SLED in UD
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot to all My Dear Friends.
Regards.
A.Mittal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Atul
Inaddition to the settings in material master & SLERD activation OMJ5 , you add Std Char : LOBM_VFDAT as a chaarecteristic for the class of class type 023/022 for the material..
Then you can get this.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Atul,
The production date of the material delivered will be entered during the goods receipt only, hence, the pop up will not appear during the UD.
Regards,
Sravan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In addition to the material master settings as updated by other memebr, you have to make settings in OMJ5 activation to be made for SLED for plant & movement type.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Go to MM01>Plant data/Store 1>shelf life data tab
Enter
Max. storage period --->Maximum period for which the material may be stored.
Min. Rem. Shelf Life-->Minimum amount of time for which the material must keep upon goods receipt for the goods receipt to be accepted by the system.
Period Ind. for SLED-->day month or week
Total shelf life----->Period for which the material will keep in total, that is, from the date of production to the shelf life expiration date.
If you maintain this System will ask you during SLED MIGO and UD
Regards
Sujit S Gujar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.