Dear all,
my client is using strategy-40
whn i am trying to find demand for any product , i could'nt find
how to check demand for the products
i used SE16- PBED & PBIM, but i could'nt find any demand
what are other tables which are used to find demand
How to process to find PIR's of the products
Regards
kumar
Dear,
For the material (MATNR), get the values of the requirements pointer(BDZEI) from table PBIM(Independent Requirements for Material)
PBHI table(Independent item history) with req.pointer(BDZEI)
Or execute transaction MD73.
Pls select option "3 :History Planned ind reqmnts " in the display options and execute the report.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
For requirements , as it is make to stock strategy that you are using now , you can check the requiremets for the currect and future periods with the T code MD63 ( display Planned independent Requirements). or If you want to past transactions then you should see MD04 ( Stock /Requiremets ) screen where you can find all the requiremets and Planned orders created for the purticular Material.
Thanks
Ankaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PIRs can be displayed in MD63... Also check the following link
[https://forums.sdn.sap.com/click.jspa?searchID=24762914&messageID=6871022]
karthick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.