Sir,

Our client is planning the material considering the Last Six months sales Average -/+ 10%

How to Map It & what are the steps involved in it Tell me in detail with T code flow

Thanks in Advance

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

former_member199502
Active Contributor
0 Kudos

Hi,

Try to do Forecast based Planning with MRP type VV,and maintaining forecast requirements in forecasting view in material master.

Selext the appropriate forecast model which meets your requirement(may be moving average or weighted moving average) and give last 6 months fert material consumption(sales-PGI done).based on this execute the forecast.

Consumption values get updated in Material master additional data consumption tab.

Refer this link about forecast based planning from the SDN forum

/community [original link is broken]

Hope this helps

Former Member
0 Kudos

Hi Girish,

The link which you had given is not clear can u please clear it.