on 04-13-2009 6:43 AM
Sir,
Our client is planning the material considering the Last Six months sales Average -/+ 10%
How to Map It & what are the steps involved in it Tell me in detail with T code flow
Thanks in Advance
Regards,
Hi,
Try to do Forecast based Planning with MRP type VV,and maintaining forecast requirements in forecasting view in material master.
Selext the appropriate forecast model which meets your requirement(may be moving average or weighted moving average) and give last 6 months fert material consumption(sales-PGI done).based on this execute the forecast.
Consumption values get updated in Material master additional data consumption tab.
Refer this link about forecast based planning from the SDN forum
/community [original link is broken]
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.