Dear Experts,

While creating the PO i don't want the price to be adopted from the Info record ..

I want to disable this function

Thanks in advanced

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

but nobodey answered

Former Member
0 Kudos

Thanks for your quick response

How could I do change the access sequence (Step by Step Please) ??

Thanks

Former Member
0 Kudos

Hi

Its very easy dear....just remove the access sequense from the basic price condition u are using in ur schema, Basically what i understand is u might be using the SAP standard basic price condition (PB00 / PBXX) these conditions are by default having access sequence assigned. Either just remove these access seq. or create another condition type a copy of the existing one but just remove access seq. and assign this condition type in ur calculation schema in place of present baseic price condition.

In SAP standard conditions there is already one condition type of Gross price for manual price (means without access seq.) u can use that also.

Hope this solves ur problem

Regards

Vineet Baweja

Former Member
0 Kudos

Still the same problem .. all I want is to make the end user to enter the price manually instead of adopting it from the PIR

Waiting for your advice

Former Member
0 Kudos

Still the same .. please see this warning message :

Net price for item 00010 adopted from last document

Message no. 06219

Diagnosis

The net price of this material was adopted from the last purchase order as default value.

Procedure

If the message is a warning, you can continue your processing.

If it is an error message, you cannot do so.

former_member581212
Active Contributor
0 Kudos

hi,

Make settings for EVO default buyer parameters...by which last Po price can be adopted but not the PIR price...

SPRO >> MM > Puchasing >> Environment data >> default parameters for buyer's EVO parameter...

Here tick for the GROSS price adoption...

Or

Don't make the Inforecord first, let it get generated from PO itself...

Regards

Priyanka.P