on 04-11-2009 12:55 PM
Please give me QM Stepwise transaction for inprocess.
Thanks
Thaks all of U
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thaks all of U
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kumaran
What is the control key you are using. Make sure that you have inspection char tick in the control key
Regards
gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello ,
I will provide you with 03 inspection setting
At plant level in Customisation maintain the following
1) Plant level - Result Recording
2) Inspection point field combination : 100
3) partial Lot Assign : Partial lot and batch for each inspection point
4) Proposal for inspection point valuation : Maintain any of the selectedset coded you have created for 03 inspection or 04 inspection
Master Data Required
1) Maintain 03 inspection in MM02
2) Selected set for 03 inspection for the particalur plant
3) Sampling procedure with selection of inspection point as this mandatory
4) Maintain routing as mentioned below
1) Go to CA02
2) go to header
3) Maintain inspection Point as 150
4) Maintain partial Lot Assign as partial lot assignment according to plant default
5) At Operation level maintain a QM work center ( testing ) with Control key QM04 ( as per your requirement)
6) double click on the control key and go to Quality Management : Inspection points
7) Maintain Inspection point completion : Quantity , Valuation and confirmation ( as per your need , you can select other options also) press F1 and see the impact of each
😎 choose time related and keep Tfac 1 and Unit as HR ( As needed)
9) You can select quantity - related also and then maintain the quantity.
10) Selection the QM operation and maintain in the MIC with above said sampling procedure
At transaction level
1) create order co01, release and save . lot will be created.
2) Do the opertion confirmation if there is any operation mentioned in the routing before the qm operation
3) go to qa32.> result > you will get a pop of all the operation with yellow traingle mentioning QM is active in that operation. double click on the QM operation
4) pop will come for entering parial quantity, date time
5)enter the details, do the result recording
6) save, pop will come for confirmation of quantity
please let me know if you need more clarification
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Samir ,
You can follow the following steps in sequence .
1) Activate inspection type 03 in QM view of Material master. ( MM02)
2) Create routing with Inspection characteristics and mention control key as PP04 ( CA01/CA02)
3) Create the production order and release the order for automatic creation of inspection lot (CO01)
4)Do result recording and take user decission (QE51n & QA11 or QA32)
This concludes your cycle for inprocess insp.
Thanks
Ankaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Samir,
-Activate inspection type 03 in the QM view Material master.
- Attach MICs to those Operation / Phases of your routing/master recipe for that material.
- Now as soon as you release your Pro. Order, system will generate an inspection lot with inspection type 03.
- Now you may procees the this lot as you process the other lots normarlly.
Let me know if you need further assistance.
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Shyamal,
if the prduction order is of 1000 qty & if I am doing confirmation for 250 qty then I must have to do inspection of 1000 qty.
How can I only inspect 250 qty & send forword for futher qty?
Here while doing UD there is no tab for inpection lot qty posting.
In case of single item flow How can we map with 03?
please Correct me if i wrong.
regards,
chandra
Hi Chandra,
make one thing sure that 03 inspection lot is stock relevant inspection type, so it will not have any stokc posting tabes in any inspection lots. But yes you can only confirm the quantity for the relevant operations according to the progress of your manufacturing process. You need to maintain the relation ship also in your recipe / routing to restic the bipass of this restriction.
Regards,
Shyamal
Hi sameer/Chandra,
In addition to steps what shyamal has suggested let me tell you that...
1.Acivate 03 in MM
2.Then create a Raouting for Insprocess if applicable.Maintain Inspection points if applicable.
3.When production order is created & release then..
03 inspection lot is generated.
Remeber 03 inspection lot is Created for full Qty what is maintaned in Production Order.
After Relaseing (or partially realseing) Prod order 04 inspection lot is created.(& not 03)
Also 03 is not stock relevent You can process 04 w/o taking UD of 03.
I hope this will help
Regards
Sujit
Hi Samir,
In Routing (CA01), maintain status as release and Usage as Production. Goto to operations and enter operation no, work center & select the control key as PP04 (ensure insp characteristic reqd indicator is active for the control key, you can check the same with OP00 Transaction in IMG).
Now select the operation line item and click on Inspection characteristic button, enter MICs or Insp char as per your requirement.
Follow the steps mentioned by Ankaiah.
You'll be able to do Inprocess inspection.
Regards,
Keerthi.
User | Count |
---|---|