Apr 11, 2009 at 10:10 AM

The target costs in target cost version 0 are missing

3388 Views

Dear Experts,

I am getting following error while running Varience cost through KKS2:

Only remaining var. in version 0 - no target costs for 000001061683 0001

Message no. KV151

Diagnosis

For the calculation of variances with 000001061683 0001, the target costs in target cost version 0 are missing for the following reasons:

There were no planned costs and/or planned quantities (see earlier message).

The quantities on which the planned costs were based are zero in the time period concerned. This may be caused by the fact that no goods receipt for a cost object (such as a product cost collector or production order) has been entered.

This results in target costs of zero.

System response

Because no target costs were calculated, the difference between the

planned and actual costs could not be broken down into variance categories. The difference is updated as a remaining variance.

Please suggest, How to proceed.

Regards