hello

I have a product with many components. These components was assigned to different operation. When I use CO11 confirm the prod. order, the components will be consumed from PSA (supply area) to production order.

If I have 1 pc product scrap in the last scarp and I confirm in system, the system will scrap all the componets in the product. But acctually I want only 1 component to be scaped, the others still can be used. How can I solve this problem?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If Iam getting it right, then during confirmation using CO11/CO11n, when you are posting Scrap 1pc for Product, all input components are getting scrapped/consumed. But, as per the requirement, only one components should follow the process.One way could be, during confirmation go to goods movement tab & delete all components except one.

Former Member
0 Kudos

Yes, I also have same opinion with you. Is there any other solution? For example, clear the difference in inventory.

Answers (2)

Answers (2)

Former Member
0 Kudos

Yes, I also have same opinion with you. Is there any other solution? For example, clear the difference in inventory.

Former Member
0 Kudos

Hi,

as per my knowledge

just maintain that one component (as component scrap in BOM) under item details

anyway's just wait for other expert's solutions