Capacity planning and evaluation period

Hi,

I have assigned two work centers with capacity category machine and labor in different activities of my project.

Now when I am going to the capacity overview the whole histogram or the bar is shown in green. This means there is no overload i think.

When I am going to the capacity load list it is giving message

"No capacity requirements were found in the evaluation period"

I have tried changing the evaluation period in spro but still not giving the load

why is this happening?

Plz help

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 10, 2009 at 04:09 AM

    Activate Cap.Requirement and then do scheduling....then check the capacity histogram....