I am working on the IM-PS integration.
I have a doubt on the use of the investment profile in the program type.
For my scenario, i have defined
1. A program type
2. Assigned a investment profile to program type apart from aal other control profiles.
3. Defined a appropriation request i.e. AR type
4. Assigned project profile and investment program type to it(Now my project profile does not have a
Investment profile associated with it)
Now when i Create AR using the above configuration and assign it to the program type, the project is
getting created with the approval of AR.
But the project created is without investment profile and hence no AUC is created when i release the
WBS element which is created by the AR.
I can understand that if i have the investment profile assigned to the project profile assigned in
AR type, the the WBS created by AR will have this investment profile.
Then my doubts are
1. What is the use of investment profile in program type and in turn in program Created?
Thanks in advance