on 04-09-2009 7:52 AM
My client requirement for overall profile in CM01 is 365 days + 60 days past. We i try to configure the same for selection profile, what i need to enter in start date and finish date. Which type of date specification G, I, J i need to select? and where we will configure the date of specification?
Dear,
Please refer this link,
[ Capacity Leveling Profile Setup |http://www.sap-img.com/pp002.htm]
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
You can define it in OPD2 and OPD0 Overall profile that is assigned in OPKP. In that profile, you can see various other profiles like Strategy profile, Control profile, Time Profile etc.. assigned to that. Double click the TIme profile and you can change the values in the Evalution period mentioned in that time profile. Save and check for your requirement.
Regards,
R.Brahmankar