PR overall release

Former Member
0 Kudos

hi,

I have configured release strategy for PR with classification. The strategy works fine for item-wise release of PR, but when i am trying to change it to overall release by selecting the indicator "OverReqRel" for the release group the release strategy is not gettign picked up. what might be reason.

regards

alexandro

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member210560
Active Contributor
0 Kudos

Dear Alexandro,

This was because you had not yet defined the "overall release" indicator for the particular

doc. type via spro-mm-pur-define doc. type. However, i will advice you not to switch on and

off this indicator once you had used it as this will create possible inconsistency if you still

had not PR's that not completed yet the business process.

For example now, you had a PR that was subject to item wise release and later on you change

this, the PR's will be affected.

Best Regards,

Ian Wong

Former Member
0 Kudos

Hi,

Please enable check box for the PR document type in spro-MM-PR-Define document type and try.

Also, check the values maintained in customisation are the same in PR.

Regards

Ram

former_member581212
Active Contributor
0 Kudos

Tick the OVRELPreq indicator ticked under the release group of the release strategy settings in the SPRO..

and then try again..

Regards

Priyanka.P