Purchase Requisition version

Dear all,

could you help me on this question?

i want to keep the PR date & Requirement date fixed under all activities in project builder, but whenever i do the scheduling or in thing like addition of new activity & then go to save project builder system shows some networks having costing error.

When i checked PR under that particular network in ME53N some of them shows new version created.

but the fact is these dates will change unexpectedly.

when i want to save the dates of all activities, i create the Purchase Requisition version. could you explain it in details?

Please do the needful as soon as possible.

thanks a lot.

Rakesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Apr 09, 2009 at 09:55 AM

    Hi,

    I think you creating network activities... you have scheduled the project...... materials you have attached to activity..... you have created material POs with Network account assigned (consumption)

    or PR through Projects directly.

    in this scenario requirement date of materail may be copied from start ( eirliest/ latest) or finished ( eirliest or latst), whenever you schedule the project system updates the date & same dates will be copied to material requirement date, if you maintain requirement date manually then scheduling will not affect the requirement date...

    so this is completely depend on scheduling & requirement date...

    I hope this will help you...

    In case of error in cost - that is nothing to do with scheduling

    just check activity cost calculation ( based on work center & activity type)

    Venkatesh