on 04-09-2009 3:46 AM
Hi Gurus,
Our client requirement is like this:
Sale Order Line Item Material Size Confirmed Qty Delivered Qty Actually want to deliver
10 X 600 1000KG 1000 2000
20 X 600 1000 1000 1500
In order to system to allow to deliver more than the actual confirmed quantity, I have given in Customer Master Unlimited Tolerance. But when he delivers, for the first line item 2000 KG then for the next line item it is saying only 0 KG of Material X is available. (even though Material Stock is available in MMBE).
How to map this scenario where, each line item should act independently, with out having impact of what delivered in the previous line item. Availability Check used is 01.
Thanks in Advance.
Best Regards
Sreekanth
No further replies
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As far I know, you can capture all the quantity you want, but SAP confirms as much as you have in your stock, no more.
Please, go to CO09 to verify the stock quantity available, you migth see that others orders had already "take it", thats the reasons that you see it on MMBE but in ATP appears al 0.
Maybe back order processing would help you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.