Budget Exceeded Message Customization

Hi, is there a user exit or customization available to change the warning/error message when the project budget is exceeded and availability control kicks off upon exceeding the budget tolerance limit?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Apr 08, 2009 at 03:07 PM

    Have u tried in

    SPRO-> Project systems-> Costs->Budget->Define Tolerance Limits

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      The Define Tolerance Limits function lets you define what you want to do - warning, warning with MAIL or error, but it does not let you specify what is going to be specified in the warning, error or in the MAIL. I am looking for ways to customize the message.

  • avatar image
    Former Member
    Apr 08, 2009 at 11:46 PM

    We couldn't change the BAC messages through customization because the underlying code is manipulating internal ABAP text fields. Another driving requirement for us was to have a single BAC email sent out per project per day.

    We controlled this by:

    1. Set BAC to warnings only

    2. Captured all BAC warings in a custom table through user exit "EXIT_SAPLBPFC_002".

    3. Run a nightly batch job that reads the posted BAC warnings and sends out the emails as needed with the text we want. This is a small custom program.

    Hope it helps,

    Phil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Philip, I think this exit is part of the customization SAPLBPFC. Is it called everytime during availability control budget check against assigned values of the WBS?