Dear Gurus,

How can I display only the critical activities in the project planning board in the gantt chart.

If through the use of filter, pls list down the steps because, i tried but could not.

If there is any other way also, pls share. I think in CNS47 i can use the filter and get the list. But can i see it in planning board??

Regards,

VDS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 08, 2009 at 09:14 AM

    Hi ,

    Go to Project planning board then

    Edit > Select > All WBS element

    then

    Edit > Show/Hide > Hide WBS element

    Now there will be only activities on screen

    Edit > Select > Aactivities

    Now apply filter

    Basic total float = 0

    Execute

    and then enter

    Only activities with 0 float will be there those r critical activities.

    Rgds

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 08, 2009 at 08:49 AM

    hi

    check whether main menu settings

    from the planning board can help your requirement

    Add comment
    10|10000 characters needed characters exceeded