relationship in activity

Dear All

In Project system i have created activities under WBS i use backward scheduling but my client requirment was without maintain relationship or any linkage between activity he required activity linkage in gantt chart is it possible pl gave ur input on this

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Apr 08, 2009 at 06:49 AM

    Hi ,

    In gantt chart i.e. Project planning board u can link the activities with the Switch connect mode option. Here u can link the activities just as we do in MS Project. Or u can maintain standard activities with those relation and copy with reference.