on 04-08-2009 7:22 AM
HI Experts,
under CK11N > cost component structre view , system is showing variable cost agaisnt activities however i did'nt plan variable activity rate in Kp26.
Regards
Tayyab,
You should check your settings at the 'Cost Components atributes'. The view of the cost break down does not depend on whta you have planned as activity type rate: fix or variable, but the fact that the cost component view/itemization configuration may be set as 'Variable Cost'.
Regards,
GG