We have a multi level configurable material which is entered in sales order.

Characteristics for the Header level VC is entered in the order;

BOM is determined using dependencies.

All characteristics for sub level VC material are inferred based on dependencies.

Two scenarios -->

I. For Multi-level VC sales order when we manually change the inferred values of sub level component before saving the order and enter header config values. Planned order not created after MRP run.

IBIN tables has only one entry.

II. For Multi-level VC sales order when we do not change the inferred values of sub level component before saving the order and only enter header config values. Planned order is created after MRP run.

IBIN tables has two entries.

Ritesh Dube, request your inputs.