Skip to Content

How to change Moving average price in accouting view at valuation cat level

Hi,

We are loading Material Master data for one client. We are using LSMW to load this object

We have uploaded u201CMoving Price (MBEW-VERPR)u201D in Accounting 1 view at valuation category level. Unfortunately incorrect value has been loaded Is it possible to change??

We donot have stock for this materials.

When I tried to do this using MM02, I understand that itu2019s grayed out field and cannot be changed in second attempt.

Let me know if there is any other procedure to handle the situation??

Rajesh Chavan

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    Posted on Apr 08, 2009 at 09:40 AM

    Hi

    You cannot change the valuation price at valuation category level using MR21/MR22. You can only update the prices at valuation type level only and system calculates the total value at valuation category level depending on stock level.

    CK11n cannot be done for MAP priced materials. It is for internally produced finished goods

    What is the necessary to update the price in material master if there is no stock? When you bring in the stock (valuation type level) then you can see price updation here.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi

      What I believe is valuation type is V, and it will be updated depending on quantity/ price. As you said there is no stock. When procure the material at valuation type level then that price will be updated at valuation category level (as present stock is zero- value you are maintaining is of no use).

      You can try in MR21 by changing the values of valuation types - but these changes will have no impact at valuation category level as stock is zero. When you bring in stock, then only price gets updated and already wrongly updated price will be erased.

      Thanks

  • author's profile photo Former Member
    Former Member
    Posted on Apr 08, 2009 at 09:41 AM

    Hi

    Please use MR21 transaction it will solve your issue since you donot have any stock. Your Query that MR21 is valid for valuated materials, for this please be informed that you can run MR21 for valuated materials also. For valuated materials it will ask additinal field entry valuation type. Please run it in the current period of the material then only you will be able to view the price other wise not.

    Cost running also will update but that is not your current case now, even we do not know whether this material will be having cost run or not.

    Best Regards

    SAM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 07, 2009 at 04:12 PM

    Hi

    You can do it in MR21 or MR22 or goods receipt will change the MAP.

    Thanks

    Rahul.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 07, 2009 at 06:54 PM

    Hi,

    Please run a costing run for the material for the planned price.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 08, 2009 at 09:01 AM

    It is not possible to update the moving price n MR21 or anyothr way..

    For updating you have to run cost...in CK11n..

    karthick

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 12, 2010 at 03:17 PM

    ok

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.