Hi,
If WBS Element is in TECO State,
We know that one cannot create and release new Material and Service Demands after TECO is set,
Also, We know that Commitments made before TECO will continue to take part in Financial Postings.
My question is, can we book Manhours and post CAT2 Entries against a WBS Element when it is in TECO State.
Regards,
Hi
When status is TECO, you can complete actual postings (commitment - Actual) like GR & IV, new transactions you cannot create (which leads to commitment).
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
status TECO (I0045) does allow confirmation.
TECO means that network is closed from logistic point of view.
If you like know what business transactions are allowed then please do following steps:
1. call transaction BS23 -> here choose status I0045
2. Do a double click directly on name I0045
In the following screen you see what business transactions are allowed/forbidden.
Kind regards
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.