Hi,

i have made following settings

Budget profile

availibiity control

type-1

overall- selected

annual- selected

tollernace limit

90 % - 1 ( warning)

100% - 2 (Warning with mail)

now in projects i am having only one 1st level WBSE

EX- ABCD-1 ( Project Definition)

ABCD-1 (1st level WSBE) 0.00 (Budget)

ABCD-2 (1st level WSBE) 0.00 (Budget)

I created PR & PO with ABCD-1-X wbse amount 500 Rs.

system not shows any error message related ot budget exceeded or any other.

but in PS system its mandatory that unless & until PR & PO have not created without budget assigned to WBS but its happened.

regards,

Aadi

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Apr 07, 2009 at 06:42 AM

    Have u assigned budget to your WBS using CJ30...u r using Avail control 1..which means avail control will activate during budget allocation...

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 07, 2009 at 06:58 AM

    Please check following,

    Budget is assigned to WBS.

    in Tolerance limit select Target groups as '++'

    in Trx OKKP check whether commitments management is active for controlling area.

    Mention the person responsible in CJ20n for WBS element.

    System status AVAC is active for WBS

    Regards,

    Nitin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 07, 2009 at 08:55 AM

    budget check functionality will be activated only when u ll do budgeting against WBS.

    If u dont do budget and create pr/po...then system will not chk budget.

    Ashis

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 07, 2009 at 09:15 AM

    Hi ,

    If u want to put budget check against WBS the System status AVAC shuld be activated against the WBS.

    this activation is depend on hw u config budget profile.As per ur settings AVAC is activated after CJ32 as u ticked on Overall and releases options in Budget profile Availability control tab.Run transaction CJBV to manually activate AVAC. n check whether PO can be created or not.

    As u can create PO/PR for WBS means u can release ur WBS before budget allocation.To avoid this u can use User satus for WBS. which will restrict the WBS release before Budgetting.User status can be customized with transaction OK02

    Rgds

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 08, 2009 at 11:50 AM

    Thanks