Apr 07, 2009 at 06:38 AM

Budget Availability Control

493 Views

Hi,

i have made following settings

Budget profile

availibiity control

type-1

overall- selected

annual- selected

tollernace limit

90 % - 1 ( warning)

100% - 2 (Warning with mail)

now in projects i am having only one 1st level WBSE

EX- ABCD-1 ( Project Definition)

ABCD-1 (1st level WSBE) 0.00 (Budget)

ABCD-2 (1st level WSBE) 0.00 (Budget)

I created PR & PO with ABCD-1-X wbse amount 500 Rs.

system not shows any error message related ot budget exceeded or any other.

but in PS system its mandatory that unless & until PR & PO have not created without budget assigned to WBS but its happened.