HI

I have a problem in ps module. my all scenario ok. During test i don't allocate budget in any WBS (through CJ30). but in project builder system allow me to generate PR & PO. according to my knowledge it is impossible to do so.

pls suggest me what is missing in my configuration.

thanks

RAKESH

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Apr 04, 2009 at 11:32 AM

    As such there is not config which automatically checks whether Budget is allocated or not.

    In Budget profile, you would have given the "Activation type" as "1" which will activate the availability control only when you allocate some budget. Only after that the budget check will be done.

    If you want to check it even before you allocate the budget, then activate the availability control manually using the T.Code CJBV when the Project is created.

    You have another option also. You can use User status to check at the time of PR and PO creation, whether Budget is allocated or not.

    Hope this answers your question.

    bye

    Pratap

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      unless untill, u do budgeting, budget check functionality will not be activated .

      provided the seetings in budget profile n tolerance limit is as per requirement.

      Ashis

  • avatar image
    Former Member
    Apr 06, 2009 at 07:29 AM

    Dear,

    The cost element you have assigned in PR,PO should be of cost element category 90 i.e.stastistical.

    And activate avilability control in budget profile .And select warning or error message for that.

    Sukhveer.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 07, 2009 at 10:05 AM

    Hi

    U have to Config User status -- OK02 . Where u hv to restrict WBS release before Budgeting.

    Rgds

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 09, 2009 at 04:48 AM

    Thanks for reply your suggestion helped me.

    Add comment
    10|10000 characters needed characters exceeded

    • Please mark which answer is correct and give points accordingly...so that when someone else faces the same problem and search this forum, he can easily find which is the correct answer and which is helpful answer to the problem.

  • avatar image
    Former Member
    Apr 09, 2009 at 12:33 PM

    Dear Rakesh,

    This is standard functionality in SAP that you can create PR and PO without allocating budget to the WBS Element.So create a user status that will prohibit the system to create PR and PO in CRTD system status.

    The steps are:

    Go to OK02 and create a user status .

    then create two statuses NBUD and BUDG.

    1.under NBUD & BUDG choose object type WBS .

    2.In NBUD Forbid the Material purchase order,Material Purchase Requistion and Release.

    3.In BUDG set Budgting and allow Release.

    So system will not allow to release a project without allocating Budget.

    Once you allocate budget system will change the status from NBUD To BUDG.

    Take care.