Planned and actual costs for material components

Dear Gurus,

I have checked a few reports in like CNS41, CN52N, S_ALR_87013543 (act/plan/var cost element wise)

but nowhere I could find the planned v/s actual costs of material components planned in the Project.

Can some one help me with some report, where I can get desired data.

Regards,

VDS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 10, 2009 at 12:01 PM

    Dear Rupesh,

    I don't think so there will be any std.report in PS module to show plan vs actual cost of material component.

    For looking plan vs actual cost in PS having many std reports but they don't show for material component.

    I think for this you need to develop a Z report which will show Plan vs Actual cost of material component.

    In CN52N report (Component overview report) you can add two fields one is for plan cost & other for actual cost.This can be one of possibilty you can try.Otherwise develop a new Z report for the same.

    For this you need to take yr abaper's help.

    Regard's

    Sandeep

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 04, 2009 at 08:31 AM

    Hi,

    The Planned /Actual cost will always displayed with respect to costelemnet only,not on the material or service you have consumed.

    In KOB1 you can see only actual consumption for material wise.

    The stock received & kept in storage you can find in MBBS.

    If the requirement is like that then you have to develop ZDevelopment for reports.

    Regards,

    Raj

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 09, 2009 at 06:30 PM

    Hi Rupesh,

    You can get from Hierarchal reports planned.actual/commitment report.

    S_ALR_87013533

    Muzamil

    Add comment