I put serial numbers os components in a production order of a material that is controled by serial number too.

Which report list the goods movement for these serial numbers of componente and its repective father material and order production.

In COOIS transaction with the "Documented Goods Movement", I can lists and to check wich serial number is in the material document.

Example: I´need to input the serial numbers of components to its father material in the CO11N.

I need to track the serial numbers of components that have been moved to a serial number of the material in the production order.

Alguém conheçe algum relatório standard que apresente as informação de número de série de componentes consumidos para determinados números de série do item da ordem.

Regards, Cláudio.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

In my understanding you need the serial numbers and the production orders in a single screen...

If that is so, it is very simple..

In SQVI, join the tables OBJK and SER05.. Selct order number,serial number,material number plant as both input and utput..

and execute..

you will get ur report...

karthick

Former Member
0 Kudos

In OPK0 already configurated "Serial Number Assignment" as a requirement.

I tryed to use the IB53, but with not success.

The message is "The IBase for material 9140 could not be determined".

I want a report to list the serial number aasignment, when i put this serial numbers in CO11N.

Thanks.

Former Member
0 Kudos

Hi,

Try IH22 its a report for Material and Serial Number Combination

Thanks

Bala

Former Member
0 Kudos

Claudio

try if COIB can help to get the information, you should use order or material number and get the tree of serial number structure

Regards

Former Member
0 Kudos

Hi,

It is possible to assign serial numbers in CO11N.

In the transation OPK0 - Single screen entry, you can define that "Serial Number Assignment" as a requirement. Then from CO11N you should launch the "As built Configuration" to establish a link between Finished Goods and Components based on the Serial Number.

Bala

Former Member
0 Kudos

Hi Cláudio,

As Bala suggested make the changes in OPK0 and then maintain the As-Buil BOM in CO11N. Once you have the As-Built BOM you can querry on that using transaction IB53.

Hope this helps.

Arvind Rishi

Former Member
0 Kudos

I´ll try to do a query in SQVI.

How is possible to use the CO11N to put serial number, would be better to have the standard report.

Former Member
0 Kudos

Ola, Cláudio

I could not find these informations in the standard SAP Reports , so I had to dig a little into the SAP tables for Serial number, SER00 to SER08 (SER03 & SER05 in your case ) and linking them thru the table OBJK, where you connect the object number with the serial number