Hi Guys,
I have created PM plans around 3000 no using LSMW. The start date that i have put are of future say first week of april and Interval is of 6 months - 12 months . Now when an running IP30 for these plan the order are not generated but are sheduled to get generated on the first call date.
How can I generete orders on the shedule start date. Is there any way.
I have also tried changing the schedule date by an LSMW in IP10 to schedule orders in back date so that the first call is in this month. But it is also not possible as it gives error " No operatations could be determined for the plan for past date "
Now I tried to chage tasklist validity key date to resolve this but new group counter are generated in this process. Now i can not update these couter in PM plan as IP02 is not supported by LSMW.
I am really stuct up.. please help
thanks
Sabyasachi