dear friends,

i have used standard values in my work center and it is assigned to activities through the cost center.i maintained the activity cost in kp26 for the period.in routing i maintained the standard values hrs .

when i create order i am not getting planned cost estimation values

it is coming 0 for the activities. and no error log is coming for cost calculation. after confirmation of the order also i am not getting the actual cost in activity header. it is showing up 0.

please suggest....

thanks.