Team,

Where does the PO picks the price? I thought the priority is

1. Contracts

2. Scheduling agreements

3. Info record.

4. last PO.

I created a value contract today and also a scheduling agreement, but when i create a PO the price is coming from info record and not from Contract. What am i missing? please advice.

Thanks,

Sarathy

chris_keating
Advisor
Advisor
0 Kudos

I do not think you have the correct product selected for the Tag.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

You need to enter contract Number manually in PO to fetch the contract conditions , it just give a warning msg that Contract for this material exist, which warn you & ask you to use that contract Number in PO.