on 04-01-2009 11:00 AM
Hi All,
Is there any way to find out as this particular cost element has been assigned to this cost element group?
Thanks & Regards
Phaneendra
Go to Table SETLEAF in SE16N or se16
Give the value in the SETCLASS feild as 0102
Execute.
There you will get a list of all the cost elements under cost element groups in your system
You can specify your controlling area in the feild Org unit
Thanks
Naveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
try kah3 - extras > check & helpfunctions...
Ambiguity Check
Check Completeness
Find in Group...
Delete Unused Groups
Delete Groups Without OrgUnit
Compare Two Groups...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to KAH3 and then give the cost element group and you can then find out the cost elements in it.
Kesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
enter KAH3 trasaction and press F4 on that field
it will display all the Cost Element Group
select the group and see whether the Cost element is added to the group or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.