Budget return at highest node (IM52 Return)

Former Member
0 Kudos

Hi,

we want to return the excess budget to the highest position id in investment management (IM52)

for example, consider we have the following position ids.

3200.

3200.10

3200.20.10

3200.20.20

3200.20.20.10

3200.20.20.20

.

.

.

I need to return the budget at 3200 leve.

I am able to return the budget at 3200.10 level.

Can you please any idea for returning the budget at 3200 level (for example)

Thanks in advance

Arun

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You can do this in IM30 T code.

If you want to take the 100 USD from the bottom position, then reduce this amount by entering -100 and then add this amount on the position to which you want to add i.e. top position by keying +100 or 100.

Prerequisite for the above - The budget from the project level need to be taken to the end node of investment program by using IM52 T code.

Hope this will help you.

Thanks

Edited by: SAP Knowledge1 on Apr 1, 2009 11:28 AM

virendra_pal
Active Contributor
0 Kudos

if the budget is returned from WBS then the process would be as follows

return budget from WBS to the position id to whihc the WBS is linked

then move the budget from that position id to any upper one