In MSEG we get the material document and in BKPF we get the Invoice document.Now is there alink how could i know for this material document ,this is the invoice posted.

Accepted Solutions (0)

Answers (7)

Answers (7)

former_member565100
Active Participant
0 Kudos

resolved.

Former Member
0 Kudos

Hi,

You can use EKBE table for the above purpose.

In the table EKBE, enter VGABE = 2 (Invoice Receipts) &

enter the material document no. in LFBNR (Document No. of a Reference Document)

material document item no. in LFPOS (Item of a reference document) &

fiscal year in LFGJA (Fiscal year of a reference document).

Now when you will execute, you will get Invoice document no. in the field BELNR.

Hope this answers your question.

former_member565100
Active Participant
0 Kudos

If a material doc number is given , i want to know what is the invoice posted for this material doc from a table.

EKBE doesnt give me invoice number if i input mdoc number

Former Member
0 Kudos

do you enter invoice item based on PO or the mat. document?

former_member565100
Active Participant
0 Kudos

Thank you all.As m,entioned i have taken Invoice base don PO item number.Resolved.

Former Member
0 Kudos

An example - PO# 1404011105 and Line item# 1. We have Material doc# 5001121396 in MSEG and accounting document for invoice 5102088564 in BKPF

In MSEG for MBLNR = 5001121396, you will get EBELN - 1404011105 and EBELP = 1

In BSEG for BELNR = 5102088564 for the entry pertaining to GR/IR account (HKONT), you will get EBELN - 1404011105 and EBELP = 1

There is the link attached between PO and POLI#

Regards

Sachin

Former Member
0 Kudos

Hi

In EKBE table, For the PO and line item, you get both GR(PO history cat. as E) and IR (PO history cat. as Q, R etc) details.You have to match the corresponding GR and IR by the quantity,posting date and price which is present in this table.

Thanks,

Vasanthan

esther_hernanz
Contributor
0 Kudos

Hi!

When you create your Purchase Order item, flag the GR-based IV indicator (EKPO-WEBRE). This way you will create a link between your goods receipt and the respective invoice. You will be able to see this link in ME23 or ME23N, in the PO item history, with the view 'GR/IR assignment'.

I hope this helps!

Esther.

former_member197616
Active Contributor
0 Kudos

Hi,

the table MSEG will give the material document number and BESG gives you the accounting document generated.Link between these two is PO.Please check if this suffies your requirement.

Former Member
0 Kudos

Hi

Goto Tcode SE16

Enter table name EKBE

Execute.

It will show the material document and accounting document against PO.

Check it out.

Regards,

Raman

former_member581212
Active Contributor
0 Kudos

hi,

check RSEG, BSAK, BSIG tables...

Also check BKPF -accounting document header...

Hope it solves your query..

Regards

Priyanka.P