How to enable Cost Element field in CJ20N

Former Member
0 Kudos

The field Cost Element in the detail screen of Service Activity is disabled. While selecting services from MSS under this activity, system asks for cost element for every line item.

In my case total PR is assigned to single cost element there is no need to enter different cost element for each line item . Is it possible to enable the field cost element on the CJ20N screen, so that system will not ask to enter cost element again while selecting services - Like in External Processing Activity

I have tried through field selection for Network, but not working.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

That is related to TAB Pages.....It doesnt affect field status.

Former Member
0 Kudos

I have already checked that, its not working.

Former Member
0 Kudos

Please, try checking settings in tx SPRO go to activity Project System/Structures/Operative Structures/Network/User Interface Settings/Layout of Activity Detail Screens/Define layout activity detail screens

Kind regards,

Neil

Former Member
0 Kudos

Cost element is not same for every WBS. There are n no. of PRs ......WBSE in one proj.

Former Member
0 Kudos

In tx SPRO go to activity Project System/Structures/Operative Structures/Network/User Interface Settings/Define Field Selection for Networks (OPUC)

In that activity you can check the fields that you need to see in your activities.

In your case you would have to select Network:Details and check as Input the Cost Element (AFVGD-SAKTO)

Hope it helps.

Neil

former_member203108
Active Contributor
0 Kudos

try this.... enter cost element in OPUU for service activity

Former Member
0 Kudos

Dear,

You should add the cost element in Network profile OPUU.

Activities tab.

Then no need to give cost element every time.

Sukhveer.