Hi,

Material 'A' with moving average price $100. Purchase order for 1 qty, price 100 and freight 10%.

Now i want stock account to be updated by $100, currently stock account gets updated by $110. material value also changed to $110.

Freight should not be included in material cost.

how to handle this.

Regards

fozters

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Mar 31, 2009 at 04:41 AM

    Hi,

    This all depends upon what Gl account u have maintained in OBYC for FR1 and FRE.

    Please change the GL account maintained in OBYC

    Regards,

    Manish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 31, 2009 at 04:42 AM

    Hi,

    Maintain Standard price procedure "S" as $100. in MMR for the particular material,

    Then stock account gets updated for 100 $ only.

    Hope it will help you,

    Regards,

    Romaesh

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Kunal Ingale

      Hi,

      I gave frieght condition type FRA1, which has account key FRE and accrual FR1.

      While doing MIGO, BSX gets debited by 110, in which 10 is freight cost. GR/IR clearing account credited with 100. Freight clearing account with credited with 10 (transaction key FR1).

      I want BSX to be debited with 100 excluding frieght.

  • author's profile photo Former Member
    Former Member
    Posted on Mar 31, 2009 at 05:22 AM

    dear sir.

    for your fright condition in M/06, check accruals key should be unclicked.

    and in pricing procedure for the fright condition statical should be clicked and give the account key FRE1.

    for FRE1 in obyc assign the G/L account.

    then it will not add to material cost when you do the MIGO.

    regards

    jrp

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.