Hi All,

I have one query:

How to make the price conditions greyed out in Shceduling Agreement of document type LP?

I even tried out making the price and price unit field display in the field selection but was of no use.

Any help highly appreciated..

Regards,

Abhijit

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please go to the document type of the Scheduling Agreement and navigate to the side...you will find the time dependent conditions check box...please uncheck that...

This will solve the issue.

Regards,

Sekhar.

Answers (2)

Answers (2)

former_member193326
Active Contributor
0 Kudos

Hi,

Please use the funtion mex_feldauswahl as described in the note 30316, then you will able to see which field selection keys are influencing the fields from the scheduling agreement.

Best Regards,

Arminda Jack

Former Member
0 Kudos

Hi

Try it out in SPRO- Material amnagement- Purchasing- Scheduling agreement - Define screen layout at document level.

Then select PT0L and change the price into dispaly.

It will work

Regards,