Rallocation plan data from Network Order

0 Kudos

Hi, Guru's!

I have a plan data on Network Orders. Settlement rule for all of NetworkOrders is a Cost Center's. I need to reallocate plan data from Network Order to CC. How it possible to do?

As far as know, is impossible reallocate Network orders in plan as for Actual CJ88 (CJ9E have not any NetworkOrders). I tried to use cycle KSUB - but it cannt find Network Order as a sender for reallocation expenses.

Accepted Solutions (1)

Accepted Solutions (1)

kenmelching
Active Contributor
0 Kudos

This is usually not done. Standard PS reports (CN41N) actually eliminate settlements and show you plan and actual costs where they occurred and not where they settled.

If you reduce the network plan costs then the standard reports will just show cost overruns.

Also, network costing does not write plan line items. it only updates the summary tables. If you have to "move" plan costs you will need a custom transaction to reduce the NWA plan.

Answers (2)

Answers (2)

0 Kudos

Ok, thank you.

As I understand, for my purpose better use next solution: use User Exit and plan the same data on CC at the moment of planning data on Network Order.

0 Kudos

Ok, thank you.

As I understand, for my purpose better use next solution: use User Exit and plan the same data on CC at the moment of planning data on Network Order.