Dear all

Can we transfer sales order stock to project stock?

If yes, which movement type?

I have already tried 415 E. Didn't work for me.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Makal
Active Contributor
0 Kudos

Issue resolved.

Thanks

Former Member
0 Kudos

Hi

I want to transfer plant stock to project stock

iam trying by 301q and 311q but not working

Pls help me out

thanks in advance

chris

Former Member
0 Kudos

Dear Chris,

Use 412 Q to transfer plant to project stock and 411 Q for reveral .

To transfer project to project use 415 Q.

Regards,

Muzamil