03-30-2009 6:04 AM
hai abapers.
i have on req ,previously we have on job.that is scheduled in background(on for specified time:23.04.2008 and time 12:00:00) but now i want to schedule this job in background for every day and send mail to concerned persons..here i want to change period values,but i couldn't find option to change the job..
03-30-2009 6:07 AM
Check if this has been hardcoded in program or check the properties of Job, You will get in either of them.
03-30-2009 6:07 AM
Check if this has been hardcoded in program or check the properties of Job, You will get in either of them.
03-30-2009 6:11 AM
yaa.ok i got it ..
it is in sm37(jobs overview ) select job you want to change .go to job ->change then it will allow the job to change mode..
03-30-2009 6:11 AM
03-30-2009 6:14 AM
Hi,
Firstly create another job and schedule it for everyday and if its successful then delete the job which was running previously...
Regards,
Siddarth