How we can upload data for asset under construction , in as91 where we can input the values if my auc is partially settled and partially under construction and its interest value.

suggest.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Create the IO / WBS and post there the values and settle it from there to the AUC

Former Member
0 Kudos

Thanks,

but where i can put the values in AUC Master. For uploading. and how my asset maSTER GET UPDATED.

Former Member
0 Kudos

hi

enter the values in Origin tab of Original value.

Former Member
0 Kudos

Hi ,

You will have to create Internal Order for Each Asset and Also you have to create one-time clearing Account.

Step1 - Create Internal Order which is Assigned to Assets.

Step2 - Post the Amount which (Account Assignment Object- Internal Order) by

following Journal Entry

Debit Clearing Account

Creit Upload Control Account

Step 3- Settle the same to AUC (WIP) Account.

Debit AUC WIP A/c

Credit Asset Clearing Account (Cost Element)

The above is the Sequence.

Hope this clarified.

regards

N.Kumar

Former Member
0 Kudos

hi

create the asset class for AUC while doing the Upload LSMW use this asset class and proceed.

Former Member
0 Kudos

Thanks,

but where i can put the values in AUC Master. For uploading.